About the Project

The project included a new segment of the highway with two lanes in each direction, bridges in a total area of approximately 16,300 m2, retaining walls, drainage channels, landscaping and system work.

The project also included:

Earthworks and paving – a two-lane 8.1 km segment of Highway 6.
Nine bridges in an area of approximately 10,500 m2.
Drainage channels.
Asphalt
Retaining walls.
Temporary and final traffic arrangements during the project.

 

Client: Netivei Israel Ltd
Period of Construction: 2013 – 2017
Financial Scope: Approximately NIS 311 million

Contact us for your next project

Read more